#325 Petaluma Bridge Construction Project

During construction of a new bridge footing in the Petaluma River, a slurry seal was poured into a caisson and did not properly set.  The contractor was required to dredge out the slurry seal prior to attempting another pour and sufficiently dewater the slurry so it could be hauled off-site.